The prevention and treatment of pneumonia epidemic in wuhan Raytheon mountain hospital was 80% complete

The prevention and treatment of pneumonia epidemic in wuhan Raytheon mountain hospital was 80% complete

June 18, 2020

Reporter from the conTractor in the construction of the third bureau learned that by the noon of February 3, wuhan Raytheon mountain hospital overall completed 80%. The isolation ward is responsible for 75% of the total workload.

Among them, all the foundation construction was completed, 1903 box room hoisting was completed, 1000 floor glue construction was completed, 200 toilets were tiled, and the installation and decoration of rooms were completed simultaneously. Medical and technical building steel structure installation completed 90%; Equipment foundation such as liquid chlorine dosing room, garbage treatment station, liquid oxygen station, positive and negative pressure station room and garbage temporary storage room were completed, and installation of sewage treatment station was completed.

The medical and living area accounts for 90% of the total workload. The main structure of 7 buildings in phase I was completed, with the installation of A1, A6 and A7 completed, and the installation of A2, A3, A4 and A5 completed by 90%. The foundation construction of the second logistics support building in phase ii was completed, and the construction of the other building was completed. Construction of the main structure of 1 expert building was completed. (map provided by China construction third bureau)

Featured

ACE Group Secures Strong Global Orders, Empowering Infrastructure Development Worldwide with Diverse Equipment Solutions

ACE Group Secures Strong Global Orders, Empowering Infrastructure Development Worldwide with Diverse Equipment Solutions

ACE Group to Make a Grand Appearance at Mining Indonesia 2026 in September

ACE Group to Make a Grand Appearance at Mining Indonesia 2026 in September

LYROAD Machinery Used Asphalt Plant Officially Operational in Central Asia

LYROAD Machinery Used Asphalt Plant Officially Operational in Central Asia

ACE Group BAP120+RAP60 Virgin & Recycled Integrated Asphalt Plant Successfully Put into Trial Production in Central Asia Project

ACE Group BAP120+RAP60 Virgin & Recycled Integrated Asphalt Plant Successfully Put into Trial Production in Central Asia Project

Trending Products

XCMG Official 5m 1000W*2 Hand Push Operated Lifting Telescopic Mobile Metal Halide Lamp Balloon Light Tower

XCMG Official 5m 1000W*2 Hand Push Operated Lifting Telescopic Mobile Metal Halide Lamp Balloon Light Tower

XCMG Official 5m Hand Push Lifting Telescopic Mobile Halogen Lamp Light Tower for Construction Site and Mining

XCMG Official 5m Hand Push Lifting Telescopic Mobile Halogen Lamp Light Tower for Construction Site and Mining

XCMG Factory 9m Hydraulic Mast Diesel Generator Trailer Mobile LED Stadium Light Tower

XCMG Factory 9m Hydraulic Mast Diesel Generator Trailer Mobile LED Stadium Light Tower

XCMG Official 7m China New Mobile Diesel Generator Explosion Proof LED Work Light Tower for Sale

XCMG Official 7m China New Mobile Diesel Generator Explosion Proof LED Work Light Tower for Sale

Engineering Machinery Vocabulary
TO TOP