Introduction: On January 25, the China Construction Third Bureau received the task of building the second wartime infectious disease hospital in Wuhan, overcoming the "year pass" and "ldquo; The epidemic situation & rdquo; simultaneously construction of Vulcan Mountain Hospital & rdquo; multiple difficulties, the first time quickly attacked again, the next night battle continued construction, the model took the lead in charge, all the will to overcome the difficulties, the whole staff to fight for fuel for life ... The Huangjia Lake in Wuhan, which is still on, has thousands of builders and nearly a thousand large machines. After 10 days and 10 nights of struggle, this total building area is 79,900 square meters and can accommodate 1,600 beds. The Raytheon Mountain Hospital & quot; Instant & rdquo; Rise , And carried out acceptance and gradually transferred on February 5.
On the first day of the new year on January 25, the construction horn of the Vulcan Mountain Hospital just blew, and the Wuhan New Coronary Virus Infection Pneumonia Epidemic Prevention and Control Headquarters urgently held a dispatch meeting and decided to build another one in Huangjia Lake, Jiangxia District, Wuhan within half a month The Thunder Mountain Hospital.
On January 25, the Standing Committee of the Political Bureau of the Central Committee of the Communist Party of China held a meeting to specifically listen to the report on the prevention and control of pneumonia epidemic of new coronavirus infection, and to re-research, re-deploy and mobilize the epidemic prevention and control, especially patient treatment.
As the central enterprise building in Hubei, the China Construction Third Bureau once again invited the enemy to take the lead, and then took the lead in fighting the Thunder God Mountain and started the Vulcan Thunder God "two-line operation".
Civil engineering site
Still fighting again for the sake of responsibility
50,000 square meters, 75,000 square meters, 79,900 square meters. Facing the fierce momentum of the epidemic, in just 6 days, the planned total construction area of Thunder Mountain Hospital increased three times, and the number of beds increased from 1,300 to 1,500. The overall scale More than two Vulcan Hill Hospital, but the construction period is comparable to Vulcan Hill, the difficulty can be imagined.
What's more, the city's existing man-machine materials are assisting Vulcan Mountain, and then opening the second battlefield is even more difficult.
Facing the difficulties, Zhou Naixiang, Party Secretary and Chairman of China State Construction Engineering Group, emphasized: "Take the power of the entire group to ensure the rapid completion of Vulcan Mountain and Thunder Mountain Hospital". & ldquo; Defend the people, defend their homes, and defend Wuhan! & rdquo; Chen Huayuan, Party Secretary and Chairman of the Third Bureau of China Construction Engineering, issued a call to all soldiers participating in the war. & ldquo; The task is given to us, we must go all out! & rdquo; Chen Weiguo, deputy secretary of the party committee and general manager of the Third Bureau of China Construction, issued the “Military Warrant”.
At 18:30 on the evening of January 25, the first batch of 50 management personnel of the Lei Shenshan Hospital project arrived at the construction site, more than 200 laborers were in place, and various preparations were quickly started. As of noon on January 26, there were 288 management personnel and 660 workers at the site. There were 36 dump trucks, 40 excavators, 10 bulldozers, 2 forklifts, and 2 ascending vehicles at the site. Reached 2000 people. At present, the site leveling work has been fully launched.
& nbsp;
Shandong Lingong E6500F under construction at Lei Shenshan Hospital
At 19:40 on the evening of the 25th, Chen Weiguo, the deputy secretary and general manager of the Party Committee of the China Construction Third Engineering Bureau and the leader of the Wuhan Municipal Anti-pneumonia Emergency Project Construction Leading Group of the China Construction Third Engineering Bureau, hurried to Raytheon after squatting for a day at Vulcan Mountain Hospital Mountain Hospital project, presided over the preparation and promotion meeting of Lei Shen Shan Hospital, and immediately established the Lei Shen Shan Hospital project construction headquarters. ,
Thunder Mountain Hospital Preparatory Conference
Two-line combat must be divided into combined strikes
At more than 4 pm on the 25th, the news of the construction of Lei Shenshan Hospital came. The company that was originally involved in the construction of Vulcan Mountain was commissioned by the company ’s third bureau and it took the lead to undertake the construction tasks of Lei Shenshan Hospital. By other sibling units.
At that time, a lot of materials purchased by a company in the early stage had arrived at Huoshanshan Hospital, and many of the materials had just been unloaded and repacked. More than 200 managers and more than 600 workers reorganized, and "rushed" overnight, and rushed to the "new battlefield". Five buses and eight trucks ran back and forth between the two hospitals, and all the transfers were completed at 4 am on the 26th, and various preparations were quickly started. Some employees expressed their feelings: I finally knew what the scene was when the PLA withdrew from Yan'an and moved to northern Shaanxi.
Labour workers enter the field
The materials on the site were not enough, and the project headquarters quickly mobilized the bureaus to affiliate regional companies to contact the sources across the country to collect materials. Take the box-type board house as an example, the unit supplier in the outer area has supplied 80% of the supply.
There is still a gap in the fighting team. The China Construction Third Bureau urgently convened all the forces in Han. "If there is a battle, the call will be returned!" "All of a sudden, the working group of all the units in the three bureaus was boiling, and the elite divisions of the first, second, third companies, general contracting companies, infrastructure investment companies, green investment companies, and installation companies of the China Construction Third Bureau were in support. For a while, the heroes of Huangjia Lake gathered and the horses galloped, and the construction situation quickly opened.
However, with the design change and scale expansion of the Lei Shenshan Hospital, the staff is still stretched. The entire China Construction Group has responded to Guangxi's "Heroic Post" in an instant and is in full support. China Construction First Bureau, China Construction Second Bureau, China Construction Fourth Bureau, China Construction Fifth Bureau, China Construction Seventh Bureau, China Construction Eighth Bureau, China Construction Railway Investment, China Construction Decoration, China Construction Engineering, China Construction Installation, China Construction The backbone of the companies affiliated to the China State Construction Group, such as West China Construction and China State Technology, rushed to assist.
800 people, 1,000 people, 2,000 people, and 5,000 people. Every increase in the number of people on the scene means that in this battle with the epidemic, we have more and more confidence. As of February 4, more than 1,000 management personnel and more than 10,000 operating personnel fought day and night. More than 1,400 various large-scale mechanical equipment and transport vehicles continued to flow. More than 3,000 box-type board houses and 3,300 sets of mechanical and electrical installation materials arrived. construction.
& nbsp;
XCMG XZ420E performs natural gas pipeline construction at Thunder Mountain Hospital
The rally blew and a day and night battle began.
The most urgent task is to get the design unit's "combat plan". The project technical team organized nearly 20 professionals to enter the design unit to design a night battle with the designers. The node diagram of the design that cannot be drawn is drawn by the project by itself, signed by the design for confirmation, and then photographed and sent to the site for construction; if the type of material is involved, the resource guarantee team must first understand whether there is a spot and then adjust the design. The traffic coordination team has coordinated tens of thousands of times per day to ensure efficient and orderly entry and exit of materials and personnel. All on-site construction personnel use the "white plus black" working mode of "5 + 2", "two shifts" 24 hours a day and night construction, competing for the progress of the project: the previous unit just completed the site Sha, the next unit will immediately enter the site to lay an anti-seepage membrane; construction and supervision personnel will be on the scene together, while communicating, designing, constructing, and adjusting. Many problems will be discussed on the spot after they are discussed hotly. A logistics support team consisting of more than 300 people is responsible for on-site three meals, three meals a day, disinfection and epidemic prevention. All personnel enter and exit the site every day without dead corner temperature measurement. All sites are disinfected no less than four times a day. Provide strong backing.
Science and the overall coordination of the race against the epidemic
In the case of a large group of soldiers, there are thousands of troops in one movement. Time is compressed to the limit. Once there is a mistake, there is no room for it. Therefore, we must plan first and plan first.
Especially for the Lei Shenshan Hospital project with complex construction content, it covers more than a dozen roads covering site leveling, foundation engineering, pipeline pre-buried, anti-seepage membrane construction, reinforcement banding, concrete pouring, board room erection, mechanical and electrical installation, interior decoration, etc. Process involving basic engineering, civil and decorative engineering, water supply and drainage and fire protection systems, power supply and distribution systems, lighting and monitoring, ventilation and air conditioning systems, communication weak electricity, medical gas engineering, purification engineering, outdoor and municipal facilities, sewage treatment facilities, etc. There are more than a dozen majors. Interfaces need to be divided between different majors. For example, designers of communication and weak electricity need to communicate with designers of power supply and distribution and civil engineering. How should optical fibers and network cables be routed? For civil construction, trenches must be pre-cut and reserved. PVC pipes, determining power supply levels; medical gas engineering designers need to communicate construction methods and containment requirements with civil decoration professionals & hellip; & hellip; ubiquitous cross-construction and interface management is a centralized inspection of China's construction management capabilities and management levels .
Coordinating tens of thousands of people, covering dozens of small processes, going through the stages of design, delivery, civil construction, equipment installation, and decoration. Many processes must go hand in hand.
As the lead unit, the three bureaus of China Construction are like the "big steward" of the project, coordinating and formulating the "road map" to victory, unified planning, organization, and coordination, and do a good job of interspersing processes of procedures and processes for all The participating units provide better services and construction arrangements to ensure that each unit can maximize its professional advantages and keep the construction pace of each unit consistent. Project inversion schedule, formulate "schedule", make each step construction plan accurate to hours or even minutes, and correct in real time according to the site conditions, so that the project management team of more than ten units with thousands of people can obey unified command, Work closely and vigorously.
The general contracting management team ensures smooth communication between all parties involved in the construction and the smooth implementation of the project construction. It has the "Xiongan First Standard" and "Fuzhou BOE" and the Shenzhen International Convention and Exhibition Center and other large corps combat experience of China Construction Third Bureau, with a mature quality control system and advanced lean construction measures, can ensure the speed of construction while ensuring the quality of the building.
Today's construction in China is no longer carried on the shoulders of people when Xiaotangshan Hospital was built 17 years ago. Today's Raytheon Hospital is no longer the Xiaotangshan Hospital of the year. Various technologies such as sewage treatment and air purification are more advanced. Patient medical personnel provide more complete life and health protection while minimizing the impact of the hospital on the surrounding environment.
Take medical wastewater treatment as an example. After the completion of Lei Shenshan Hospital, it is estimated that 1,200 tons of wastewater will be generated daily, and all of them will be closed. It can be discharged after a series of disinfection and biochemical treatments. standard. Rainwater is collected separately, entered the storage tank for unified disinfection, and the sludge is disposed of safely and harmlessly. An HDPE barrier membrane is also laid below the entire hospital to ensure that no drop of sewage enters the ground or water bodies.
Zhang Yanling, the former director of Beijing Xiaotangshan Hospital and the current consultant of the construction of Lei Shenshan Hospital, said: "The construction of Lei Shenshan is higher than" Liaotangshan ". If Beijing was an" encounter battle ", now Wuhan played a "blocking battle".
On January 27, the construction of Wuhan Lei Shenshan Hospital was fully rolled out.
Leveling work at the site of the Raytheon Hospital project
Groove graded gravel backfill
Concrete placement
As of 12:00 noon on January 28, excavation of pipeline trenches and installation of beret beams in the medical isolation area of the Lei Shen Shan Hospital Project of the China Construction Third Bureau were all completed. Start earthwork backfilling, HDPE membrane construction, and board room construction for medical staff.
& nbsp;
HDPE film laying
Earthwork backfilling
Construction of board room in medical staff's accommodation area
On January 29, the total construction area of Wuhan Lei Shenshan Hospital was expanded to about 75,000 square meters, and the maximum number of hospital beds was about 1,600.
According to the latest design, the total construction area of Lei Shen Shan Hospital has been expanded to approximately 75,000 square meters. The medical isolation area is about 52,200 square meters, with over 1,500 beds (up to about 1,600 beds); the medical accommodation area is about 9,000 square meters, which can accommodate about 2,000 medical staff; medical and nutrition restaurants, cleaning supplies warehouse (existing Construction) is about 13,700 square meters.
Lei Shenshan Hospital Project Panorama
As of 16:00 on January 29, the trench pipelines in the medical isolation area of Lei Shenshan Hospital project were pre-embedded, and HDPE film construction under the board room was basically completed, and the strip foundation was over 40%. Refit, nearly 20 have been hoisted. The steel structure foundation of the medical and nursing accommodation area has been completely completed. The wall installation of 1, 2, and 7 dormitories has been basically completed, and the remaining dormitory walls have been almost completed. Water, electricity and waterproofing have entered the site.
& nbsp;
Striped foundation reinforcement
& nbsp; The wall installation of buildings 1, 2, and 7 in the medical dormitory area is basically completed
On January 30, the overall construction progress of Wuhan Lei Shenshan Hospital was completed by 40%.
As of 12:00 noon on January 30, the overall construction progress of the Lei Shenshan Hospital project was 40% complete. The leveling of the isolation ward area, trench excavation, trench pipeline pre-buried, and PE film construction in the non-trenched area have been completed, trench backfill has been completed by 90%, and strip foundation construction has been completed by 60%. A total of 1,518 containers entered Approximately 300 sets of off-site conversions have been completed, and 30 of them have been hoisted on site. Buildings A1-A7 of the medical staff's living area completed 70% of the construction of the beams and columns, floor slabs, wall slabs and roof slabs of the board room.
60% completion of strip foundation construction in isolation ward area
On-site lifting of 30 box-type board rooms in the isolation ward area
Construction of board room structure in medical and nursing accommodation area
On February 1, the construction of the Lei Shen Shan Hospital, which was constructed by the China Construction Third Bureau, began construction of the superstructure.
/> p>
As of 12:00 on February 1, the overall progress of the Thunder Mountain Hospital project was 65% complete. The quarantine area is 60% complete, with a total of 3300 containers, and 2530 have arrived. At present, the total progress of the civil works is about 60%. Isolation ward site leveling, trench excavation, trench pipeline pre-buried, trench backfill, main pipeline surface pouring, PE film construction in non-trench area has been completed; 90% PE film in trench area is completed; strip foundation construction 95% completed; concrete pouring of the bottom plate of the sewage treatment station was completed; concrete pouring of the base plate of the medical technology building was completed, and the installation of steel columns was completed 40%. 310 containers have been hoisted on site, and pipeline installation in the room has been carried out. 80% of the living area of the medical staff has been completed, and all 398 K board rooms in the living area have arrived. The main structures of A1-A7 are all completed, and the installation parts have been put into construction. Among them, the installation of A1, A2, A6, and A7 is 50% completed; the installation of A3 is 20%; and the installation of A4 and A5 is 40%.
Concrete pouring is basically completed
Ward structure lifting
As of 12:00 noon on February 4th, the Raytheon Mountain Hospital project undertaken by the China Construction Third Bureau has progressed smoothly, and the lifting of the board room in the isolation ward area of the Raytheon Mountain Hospital is about to be completed.
/> p>
The isolation ward area has completed 85% of the total workload, and 3005 box-type board rooms have been hoisted and completed 2901, with a completion rate of 96.5%. Floor glue construction has been completed to 1,100, bathroom tiled 300, and the installation and decoration of the room have been completed simultaneously; the steel structure installation of the medical technology building has been basically completed, and the roof panel installation has been basically completed; the liquid chlorine dosing room, garbage disposal station, liquid oxygen The basic equipment of the station, the positive and negative pressure station room, the garbage temporary storage room is completed, the sewage treatment station equipment is installed and the pipeline installation is completed 80%; the positive and negative pressure station room equipment is installed 50%.
95% of the total workload was completed in the healthcare living area. The main structure of 7 buildings in the first phase is completed, the installation of A1, A6, and A7 is completed, and the installation of A2, A3, A4, and A5 is basically completed; the construction of the main structure of 2 logistics support buildings in the second phase is 85% completed; .
Box-type board room installation
Main building of expert building completed
The strategic partner of Dingli Hongxin Jianfa immediately mobilized and rushed to the site with Dingli equipment for the first time. With the help of Dingli equipment, the construction of steel structures, high-altitude welding, and internal soft mounting & hellip; was rapidly advancing.
The construction of Lei Shen Shan Hospital has entered a sprint period
As of 12:00 noon on February 3, Wuhan Lei Shenshan Hospital, which was constructed by the China Construction Third Bureau, had completed 80% of the whole and entered the sprint stage. The isolation ward area completed 75% of the overall workload. Among them, the foundation construction is all completed, 1903 box-board rooms have been hoisted, the floor glue construction has been completed to 1,000 rooms, the bathroom has been tiled to 200 rooms, and the installation and decoration in the room have been completed simultaneously; the steel structure installation of the medical technology building has been completed by 90%; liquid chlorine The basic facilities of the dosing room, garbage treatment station, liquid oxygen station, positive and negative pressure station room, and temporary storage room for garbage are completed, and the sewage treatment station is installed. 90% of the total workload is completed in the medical and living area. The main structure of 7 buildings in the first phase is completed, the installation of A1, A6, and A7 is completed, and the installation of A2, A3, A4, and A5 is completed 90%; the foundation construction of the 2 logistics support buildings in the second phase is completed, and the construction of the other structure is completed; Construction of the main structure of an expert building was completed.
ICU sickbed paving
Construction of the second phase of the medical and living area
As the main force of construction, Sany cranes participated in the installation of box transformers and 10 kV ring net boxes.
Lei Shenshan Hospital conducts acceptance and gradually transfers
After ten days and nights of hard work, on the afternoon of February 6, Wuhan Urban Construction Bureau, together with the Municipal Health and Health Committee, organized the Real Estate Group on behalf of the Lei Shenshan Hospital project, and the China Construction Third Bureau of the contractor to carry out the acceptance of Lei Shenshan Hospital and gradually transferred it.
Laboratory Department in Medical Technology Building
The Raytheon Hospital project has a particularly large amount of work, requires high functional standards, and has a particularly tight construction period. After receiving the task, the China Construction Third Bureau quickly mobilized to overcome many unimaginable problems such as personnel organization difficulties, shortage of materials and equipment, and transportation obstacles caused by the Spring Festival holiday, epidemic traffic control, etc., and entered the construction site on January 27. The project construction was promoted against time and time, and more than 10,000 people were mobilized to fight at the shore of Huangjia Lake, demonstrating the heroic spirit of the party members, cadres, and employees, who can fight hard and be good at hard battles.
In the dispatch of the first, second, fourth, fifth, seventh, eighth, China Construction Decoration, China Construction Science and Technology, China Construction Installation, West China Construction, China Construction Technology and other brother units quickly assisted the construction of Lei Shenshan Hospital, launched After a difficult general assembly battle, he wrote a heroic song of tenacious struggle.
/> p>
The ten days and nights of Lei Shenshan's struggle witnessed that China Jianjian has made its due contribution to the Wuhan Municipal Party Committee and the Wuhan people and resolutely won the fight against the epidemic.
Smoke smoke, dawn is now
Heroes build the Great Wall of Life
The winter will end and the spring will bloom.
XCMG: Six bridges and two engines, XCA400L8 _ 1 is high-tech!
Set a New National Record, Sinotruk Heavy Truck Export Exceeds 14000 Vehicles in February!
Renovation of Patterns? Zhonglian Mining Machine "Customer Activity Day" Officially Opened
Good news of delivery | Batch delivery of 30 SJM 3090F wide-body dump trucks
XCMG Official 5m 1000W*2 Hand Push Operated Lifting Telescopic Mobile Metal Halide Lamp Balloon Light Tower
XCMG Official 5m Hand Push Lifting Telescopic Mobile Halogen Lamp Light Tower for Construction Site and Mining
XCMG Factory 9m Hydraulic Mast Diesel Generator Trailer Mobile LED Stadium Light Tower
XCMG Official 7m China New Mobile Diesel Generator Explosion Proof LED Work Light Tower for Sale