SZSeries linear vibrating feeder is the common equipment in the production line of mineral processing.,It conveys material by vibration.,Because the equipment is prone to resonance during starting and stopping.,Easy loosening of accessories,Therefore, the foundation and fasteners of the equipment shall be properly installed.,What is the right way??Let's take a look.。
1、Please note before installation
Before installation,We need to confirm that the project foundation meets the construction standards in the foundation documents provided by Shaorui Heavy Industry.。
The weight of the project foundation shall be at least 3 times heavier than the feeder,To lower the resonant frequency,While shortening the resonance duration.。
The spring seat shall be fixed on the foundation bolt,Use two nuts or weld firmly on the embedded steel plate。
Warning:Do not install or weld any accessories on the body of the feeder(Uch as a hopper、Funnel、Operating platform, etc.)。These components must be secured to their respective support structures,But must not come into contact with the feeder。
2、Specific Installation Requirements
During the time of starting and stopping the feeder,The equipment will swing irregularly,It is necessary to ensure the vibration unit、Sufficient free space between other structures and equipment。So we have some specific installation requirements.:
Confirm the minimum space required when the feed chute is stationary:Side-50mm、Longitudinal direction-80mm、Vertical direction-100mm;
Pillars or other structures under the exciter must not be in contact with the feed chute;
Hopper“B”The discharge port shall be smaller than the vibrating unit.“A”The width of the,As shown in the figure below:
If a chain or discharge guide is installed, allow the feed to flow smoothly,Hopper discharge portShould notExtend too close to the feeder floor;
Feed Chute(Silo)The shall be designed to carry a portion of the feed,The blanking point shall not directly impact the tank body of the equipment.,Longer service life of equipment;
All equipment must comply with local safety regulations.;
Pay attention to:Welding on both side plates is prohibited。Otherwise, no warranty will be given for the equipment。
3、Installation of coupling
Install the coupling in the correct assembly sequence as follow:
①The black coupling is left inside
②Rubber band in the center section
③Fixed disk,Stay outside。After the host is installed,The main shaft is 0 higher than the motor shaft in no-load state-20mm。
The reference distance is shown in the figure below.:
④ After installing the coupling,Install the protective cover,Prevent the rotating parts of the coupling from causing personal injury;
At last,Please pay attention to rotating the motor in the following direction:
Take care of your device anytime, anywhere,For more information,You can also contact your local distributor or the Shaorui service team.。
XCMG: Six bridges and two engines, XCA400L8 _ 1 is high-tech!
Set a New National Record, Sinotruk Heavy Truck Export Exceeds 14000 Vehicles in February!
Renovation of Patterns? Zhonglian Mining Machine "Customer Activity Day" Officially Opened
Good news of delivery | Batch delivery of 30 SJM 3090F wide-body dump trucks
XCMG Official 5m 1000W*2 Hand Push Operated Lifting Telescopic Mobile Metal Halide Lamp Balloon Light Tower
XCMG Official 5m Hand Push Lifting Telescopic Mobile Halogen Lamp Light Tower for Construction Site and Mining
XCMG Factory 9m Hydraulic Mast Diesel Generator Trailer Mobile LED Stadium Light Tower
XCMG Official 7m China New Mobile Diesel Generator Explosion Proof LED Work Light Tower for Sale