September 5
6 occurred in Luding County, Ganzi Prefecture, Sichuan.Magnitude 8 earthquake
Road from Moxi Town, Luding County to Hailuogou Scenic Area
Interrupted by a landslide
In order to open up rescue channels as soon as possible
Several excavators race against time.
Break through on the precipice“Life passage”
↓↓↓
“One side is the mountain,On one side is the river valley
We will repair the road in the middle.”
Feng Lin, a rescue worker at the scene, introduced
Their construction site is located at
Moxi Town, Luding County, leading to Hailuogou Scenic Area
The only main road
Only this road was cleared.
Only in this way can a large number of trapped people be transferred in an orderly manner.
△Unrepaired road section
After receiving the rescue mission on the 5th
Feng Lin's rescue team rushed to the scene at the first time.
Because the road condition was unknown that night.
To ensure the safety of rescue personnel
The rescue team started work early the next morning.
Each excavator has two excavator masters.
Work in turn,Until 8 o'clock that night.
There was no pause.
△Rescue Team of Kangding Transit Section of Yaye Expressway of Shudao Group
“We're halfway up the mountain.
Visually, there is a vertical drop of 50 meters from the valley below.
It's like being on a cliff.
One side is the mountain,On one side is the river valley
We will repair the road in the middle.”
As of the evening of the 7th
The rescue team grabbed the passage road for more than 2000 meters.
Although there are still a lot of landslide in the main roads.
But without the rockfall,
Rescue workers can get through the main road.
A path leading to the river for rescue.
“As long as we get the job done.
No matter what, we must do it.”
Feng Lin said,Large amount of collapse on site
Limited working surface
The difficulty of the excavator operation.
At the scene,4 excavators in total
Linkage operation with 2 loaders
“These excavators are delivered to the site by professional trailers.
First, an excavator is used to excavate the slope above the road.
Risk elimination of dangerous rocks
Excavator is used for the buried road below、Loader
Linkage operation construction,Clear the way”
Due to time constraints
To clear the road as soon as possible.
Stepped linkage operation is adopted on site.
“The place of the landslide is a slope.
We use the excavator to divide it into layers.
Multiple excavators work in different steps at the same time”
In the process of rescue
There were several aftershocks at the site.
From time to time, falling rocks rolled down the precipitous cliff.
Excavator master needs to be more careful.
Feng Lin said
All everyone wants is to get through this road.
“What the players have said to me the most is
‘No matter how dangerous it is ahead.
Have the confidence to complete the rescue task.’”
Open the way in every mountain,Every minute counts
The excavator master has worked hard.,Be safe
To the workers fighting in the front line of rescue
Salute!
(Source:CCTV News Wechat Public Number)
XCMG: Six bridges and two engines, XCA400L8 _ 1 is high-tech!
Set a New National Record, Sinotruk Heavy Truck Export Exceeds 14000 Vehicles in February!
Renovation of Patterns? Zhonglian Mining Machine "Customer Activity Day" Officially Opened
Good news of delivery | Batch delivery of 30 SJM 3090F wide-body dump trucks
XCMG Official 5m 1000W*2 Hand Push Operated Lifting Telescopic Mobile Metal Halide Lamp Balloon Light Tower
XCMG Official 5m Hand Push Lifting Telescopic Mobile Halogen Lamp Light Tower for Construction Site and Mining
XCMG Factory 9m Hydraulic Mast Diesel Generator Trailer Mobile LED Stadium Light Tower
XCMG Official 7m China New Mobile Diesel Generator Explosion Proof LED Work Light Tower for Sale