20.161 billion yuan! Transportation Construction Plan of Rizhao City in 2023 Released

20.161 billion yuan! Transportation Construction Plan of Rizhao City in 2023 Released

January 30, 2023

Recently,The reporter learned from Rizhao Transportation Bureau.,Transportation Construction Plan of Rizhao City in 2023 Released。This year,The total investment of Rizhao Transportation Construction Plan Project is 1171.1.9 billion yuan,Annual planned investment completed: 201.6.1 billion yuan,Focus on the construction of 39 transportation infrastructure projects。Among,9 railway construction projects,11 highway construction projects,18 port construction projects,1 airport project。

9 railway construction plans,Among them, there are 2 renewal projects.,Four new projects have been started,3 early stage projects。The total investment is 261.3.4 billion yuan,Investment planned to be completed in 2023 58.1.1 billion yuan。

1.Rizhao Station Passenger Transport Facilities Reconstruction Project(Continue to build)。Investment 19.2.1 billion yuan。The construction period is from 2021 to December 2024,An investment of 800 million yuan is planned to be completed in 2023.。

2.Capacity Expansion and Reconstruction Project of Pinglan Railway(Continue to build)。The total length is about 32.97 kilometers,Investment 20.5.1 billion yuan。The construction period is from 2021 to December 2023,Investment planned to be completed in 2023 9.5.1 billion yuan。

3.Weifang-Suqian Railway Project of Beijing-Shanghai high-speed railway Auxiliary Passage(New construction)。About 49 in Rizhao.8 kilometers,Wulian North Station、Juxian North Railway Station,The investment is about 94.4.2 billion yuan。Construction period: November 2023 to June 2028,An investment of 2.6 billion yuan is planned to be completed in 2023。

4.Qingdao-Beijing-Shanghai high-speed railway Auxiliary Passage Railway Project(New construction)。About 15 in Rizhao.34 kilometers,The investment is about 25.600 million yuan。Construction period: November 2023 to June 2028,Investment planned to be completed in 2023 10.600 million yuan。

5.Railway Project in South Operation Area of Lanshan Port Area, Rizhao Port(New construction)。Track laying mileage is about 20.8 km and supporting facilities,Investment 8.600 million yuan。The construction period is from July 2023 to July 2025,Investment planned to be completed in 2023 1.500 million yuan。

6.Rizhao Port Shijiu Port Area South Railway Phase II Project(New construction)。Track laying mileage of about 20km and supporting facilities,Investment 2.500 million yuan。Construction period: November 2023 to December 2024,Investment planned to be completed in 2023 1.500 million yuan。

7.Wulian North Station Supporting Facilities Project of Beijing-Shanghai high-speed railway Auxiliary Passage(Early stage)。Construction of bus passenger transfer center,Including tourist distribution centres、Special agricultural products and tourism products exhibition hall and other facilities;Supporting construction of parking spaces for public transport and social vehicles、Gas stations, etc。Supporting construction of Zhanqian Avenue、Sichuan Road、Yingbin Road, etc。The investment is about 600 million yuan.,Carry out preliminary planning demonstration in 2023,Completed investment 0.500 million yuan。

8.Beijing-Shanghai high-speed railway Auxiliary Passageway Juxian North Station Comprehensive Passenger Transfer Hub Construction Project and Other Supporting Infrastructure Projects(Early stage)。Construction of high-speed railway Passenger Transport Service Center、Passenger distribution and transfer center、Maintenance security inspection center、Supporting infrastructure such as supporting housing,2000 parking spaces and 600 supporting charging piles and other related ancillary facilities。The investment is about 7.500 million yuan,Carry out preliminary planning demonstration in 2023,Completed investment 0.500 million yuan。

9.Rizhao-Beijing-Shanghai high-speed railway Auxiliary Passage Railway Project(Early stage)。The planned line is led from Beisongyuan Line Station.,Connect to Wulian North Station,The total length is about 55 kilometers.,The investment is about 7.7 billion yuan,Carry out preliminary planning demonstration in 2023。

11 highway construction plans,Among them, there are 2 renewal projects.,8 new projects started,1 item of previous project。Total investment 341.5.6 billion yuan,Investment planned to be completed in 2023 89.200 million yuan。

(One)National and provincial highway projects

1.Lanshan Port Dredging expressway Project(Continue to build)。The total length is about 12 kilometers.,Four lanes in both directions,Investment 24.6.6 billion yuan。The construction period is from 2021 to December 2024,An investment of 1.5 billion yuan is planned to be completed in 2023.。

2.G15 Shenhai expressway Liangcheng-Fenshui Section Expansion Project(New construction)。The total length is about 61 kilometers.,Eight lanes in both directions,Investment 83.500 million yuan。Construction period: June 2023 to June 2026,An investment of 3 billion yuan is planned to be completed in 2023.。

3.Dongliang Expressway Rizhao Section Project(New construction)。The total length is about 73 kilometers.,Four lanes in both directions,The investment is 10.6 billion yuan。Construction period: October 2023 to October 2026,An investment of 1 billion yuan is planned to be completed in 2023.。

4.Linri expressway Project(New construction)。The total length is about 20 kilometers.,Six lanes in both directions,The investment is 4.2 billion yuan。Construction period: December 2023 to December 2026,An investment of 500 million yuan is planned to be completed in 2023.。

5.West Extension Project of Shugang Road of Rizhao Port on Provincial Highway 220(New construction)。It is 57 kilometers long,Investment 34.500 million yuan。Construction period: August 2023 to December 2025,An investment of 1.5 billion yuan is planned to be completed in 2023.。

6.Reconstruction and Expansion Project of Rizhao Section of National Highway 518(New construction)。It is 24 kilometers long,Investment 16.500 million yuan。Construction period: December 2023 to December 2026,Investment planned to be completed in 2023 2.500 million yuan。

7.Large and medium maintenance works of national and provincial highway(New construction)。Route maintenance mileage: 50 km,The investment is 100 million yuan,Completed in 2023。

8.Reconstruction Project of Wuliancheng District of Fengfeng Line of National Highway 342(Early stage)。The total length is about 32 kilometers.,First-class highway,Investment 19.400 million yuan,Carry out preliminary planning demonstration in 2023。

(Two)Port collection and distribution highway project

9.Shijiu Port Area Collection and Distribution System Optimization and Upgrading Project Phase I(New construction)。Composed of 2 subdivisional works:One interchange is set up between Linyi South Road and Shugang Expressway;One interchange is set up between Linyi South Road and Shenzhen Road,Investment 2.400 million yuan,Completed in 2023。

(Three)Rural Road Project

10.Viaduct Project of Rigang Section of South Coastal Highway(Continue to build)。It starts from the right-turn ramp of Longwang River Interchange on Shugang Avenue.,Stop at the intersection of Anlan Avenue and South Coastal Road,Total length 3.48 kilometers,Ten lanes in both directions。One viaduct is set along the whole line.,Six lanes in both directions,Two-way four-lane ground auxiliary road,Total investment 6.600 million yuan。The construction period is 2022 to December 2023.,Investment planned to be completed in 2023 3.300 million yuan。

11.Other rural road construction and maintenance projects(New construction)。The road network has been upgraded by 126 kilometers.,Reconstruction of 17 dangerous bridges,185 km of security works。An investment of 500 million yuan is planned to be completed in 2023.。

18 port construction plans,Among them, there are 14 renewal projects.、Three new projects have been started,1 item of previous project。The total investment is 566.7.9 billion yuan,Investment planned to be completed in 2023 54.300 million yuan。

1.Supporting Ore Terminal Project of Rizhao Iron and Steel Quality Base(Continue to build)。One new 400,000-ton iron ore berth and supporting project,Investment 28.200 million yuan。Construction period from 2016 to December 2024,An investment of 300 million yuan is planned to be completed in 2023.。

2.Supporting finished product wharf project of Rizhao Iron and Steel Quality Base(Continue to build)。Construction of two 40,000-ton、Two 10,000-ton general cargo berths and supporting projects,Investment 22.100 million yuan。The construction period is from 2018 to December 2023,An investment of 100 million yuan is planned to be completed in 2023.。

3.South Basin Channel Project in North Operation Area of Lanshan Port Area of Rizhao Port(Continue to build)。Construction of one-way channel for 300,000-ton bulk carrier,Length 13.95 kilometers,Investment 17.8.3 billion yuan。The construction period is from 2019 to December 2024,An investment of 100 million yuan is planned to be completed in 2023.。

4.General Berth Project of North No.2 Jetty in North Operation Area of Lanshan Port Area, Rizhao Port(Continue to build)。Construction of one 40,000-ton、Three 100,000-ton general berths,Investment 16.300 million yuan。The construction period is from 2020 to December 2024,An investment of 300 million yuan is planned to be completed in 2023.。

5.South Operation Area of Lanshan Port Area, Rizhao Port#18、#20、#22 General Berth Works(Continue to build)。Construction of two 100,000-ton general berths,One 200,000-ton general berth and corresponding supporting equipment,Investment 11.500 million yuan。Construction period 2022 to December 2024,An investment of 200 million yuan is planned to be completed in 2023.。

6.Lannan, Lanshan Port Area, Rizhao Port#17 Berth works(Continue to build)。Construction of a 200,000-ton general bulk cargo berth(Hydraulic structure 250,000-ton)And related supporting facilities,Investment 4.700 million yuan。The construction period is 2022 to December 2023.,Investment planned to be completed in 2023 0.4.5 billion yuan。

7.Reconstruction and Expansion Project of Bulk Grain Storage and Transportation System in South Operation Area of Lanshan Port Area of Rizhao Port(Continue to build)。Construction of one 1200 tons/Unloading double track per hour,18 cement silos with a capacity of 10,000 tons each,2 car loading towers,1 loading building,9#Berth handling capacity of 6.9 million tons/Year,Investment 7.9.6 billion yuan。The construction period is 2022 to December 2023.,In 2023, it is planned to complete 0..4.5 billion yuan。

8.Lannan, Lanshan Port Area, Rizhao Port#Automation transformation project of handling process system in the rear storage yard of Berth 11(Continue to build)。Construction of 7 ore storage yards and their supporting dedusting pump houses、Pond、Substation, loading building and other supporting facilities,Annual turnover of 15 million tons,The investment is 1.7 billion yuan。The construction period is from 2020 to December 2024,An investment of 200 million yuan is planned to be completed in 2023.。

9.South Storage Yard Construction Project of Nanyi Jetty in South Operation Area of Lanshan Port Area of Rizhao Port(Continue to build)。Construction of 740,000 square meters storage yard、Road hardening and complex building、Substation and other ancillary facilities,Investment 5.500 million yuan。The construction period is 2022 to December 2023.,Investment planned to be completed in 2023 1.500 million yuan。

10.Rizhao Port Shijiu Port Area East Process Engineering(Continue to build)。Relying on the east of Shijiu Port Area#7、#9 Berths are provided with 2 wharf belt conveyors and supporting equipment and facilities,Realize 2 specialized storage yards,2 simple storage yard lines,Investment 4.800 million yuan。The construction period is 2022 to December 2023.,It is planned to complete the investment of 300 million yuan in 2023.。

11.Rizhao Port Grain Base Project(Continue to build)。Reconstruction of a 100,000-ton special berth for bulk grain,41 new buildings1.20,000-ton grain silo,Total storage capacity 49.20,000 tons,And supporting the construction of corresponding facilities,Investment 14.400 million yuan。Construction period 2022 to December 2024,An investment of 500 million yuan is planned to be completed in 2023.。

12.South of Shijiu Port Area, Rizhao Port#14#15 Berth Storage Yard Expansion Project(Continue to build)。Replace the 12 gantry cranes of the wharf with 6 grab ship unloaders and expand 6 specialized ore storage yards on the west side of the existing specialized storage yard.,Investment 15.600 million yuan。The construction period is 2022 to December 2025.,Investment planned to be completed in 2023 2.500 million yuan。

13.Reconstruction Project of Container Terminal in Shijiu Port Area of Rizhao Port(Continue to build)。Renovate the west area#9—#14 The bulk cargo berth is a special berth for containers.,Supporting construction of remote control quayside bridge、Rail crane、Automated storage yard、Remote control building, etc,Investment 26.500 million yuan。The construction period is from 2020 to December 2023,An investment of 400 million yuan is planned to be completed in 2023.。

14.East-South Coal Transfer Project in Shijiu Port Area of Rizhao Port(Phase two)(Continue to build)。Transform South 8#The berth is a specialized coal launching berth.,Construction of one wagon tipper house and related supporting facilities,Newly purchased 2 car dumpers、2 ship loaders,Designed annual throughput of 25 million tons。Investment 14.500 million yuan。Construction period 2022 to December 2024,Investment planned to be completed in 2023 1.400 million yuan。

15.Lanshan Port Area, Rizhao Port LNG Terminal Project Works(New construction)。Includes a receiving station、Channel、Breakwater,The construction scale is LNG 3 million tons landed/Year,Investment 64.900 million yuan。The construction period is from June 2023 to December 2026,An investment of 600 million yuan is planned to be completed in 2023.。

16.Rizhao Port Transformation and Upgrading Project(New construction)。Newly built in Phase I of the Project#9—#13、#16、#17 Berth 10—300 thousand tons of coal、There are 7 berths and supporting storage yards for ore and general use.。The second phase will be east of Shijiu Port Area.、The function of the northeast operation area is transformed into passenger transport and containers.,The investment is 27.8 billion yuan。Construction period: June 2023 to December 2029,An investment of 1 billion yuan is planned to be completed in 2023.。

17.Rizhao Port Production Facilities Upgrading Supporting Project(New construction)。For the storage yard in the port area、Road、Upgrading and transformation of production facilities such as factory buildings,The investment is 1 billion yuan。Construction period: January 2023 to December 2024,An investment of 800 million yuan is planned to be completed in 2023.。

18.Lanshan Port Area, Rizhao Port LNG Export Pipeline Project of the Terminal(Early stage)。The new export pipeline is about 39 kilometers.、It passes through Donggang District、Lanshan District,And is communicate with that Qingning pipeline.,The investment is 700 million yuan,Carry out preliminary planning demonstration in 2023。

One airport construction plan,Shandong Navigation Industry Demonstration Center Project(Early stage)。The project is located on the west side of Rizhao Airport.,45 mu,Planning and construction of 13000 square meters of comprehensive security building,5000 square meters of navigable aircraft hangar,1600 sqm UAV hangar,11000 square meters of apron and related supporting facilities。Total investment 1.500 million yuan,Carry out preliminary planning demonstration in 2023。(Dazhong Daily client reporter Li Shenghao reported)

Featured

XCMG: Six bridges and two engines, XCA400L8 _ 1 is high-tech!

XCMG: Six bridges and two engines, XCA400L8 _ 1 is high-tech!

Set a New National Record, Sinotruk Heavy Truck Export Exceeds 14000 Vehicles in February!

Set a New National Record, Sinotruk Heavy Truck Export Exceeds 14000 Vehicles in February!

Renovation of Patterns? Zhonglian Mining Machine "Customer Activity Day" Officially Opened

Renovation of Patterns? Zhonglian Mining Machine "Customer Activity Day" Officially Opened

Good news of delivery | Batch delivery of 30 SJM 3090F wide-body dump trucks

Good news of delivery | Batch delivery of 30 SJM 3090F wide-body dump trucks

Trending Products

XCMG Official 5m 1000W*2 Hand Push Operated Lifting Telescopic Mobile Metal Halide Lamp Balloon Light Tower

XCMG Official 5m 1000W*2 Hand Push Operated Lifting Telescopic Mobile Metal Halide Lamp Balloon Light Tower

XCMG Official 5m Hand Push Lifting Telescopic Mobile Halogen Lamp Light Tower for Construction Site and Mining

XCMG Official 5m Hand Push Lifting Telescopic Mobile Halogen Lamp Light Tower for Construction Site and Mining

XCMG Factory 9m Hydraulic Mast Diesel Generator Trailer Mobile LED Stadium Light Tower

XCMG Factory 9m Hydraulic Mast Diesel Generator Trailer Mobile LED Stadium Light Tower

XCMG Official 7m China New Mobile Diesel Generator Explosion Proof LED Work Light Tower for Sale

XCMG Official 7m China New Mobile Diesel Generator Explosion Proof LED Work Light Tower for Sale

Engineering Machinery Vocabulary
TO TOP