In order to implement 33 policies and measures to stabilize Tianjin's economy in the first quarter,,Accelerate the construction progress of Tianjin-Weifang high-speed railway,Recently,Tianjin Transportation Commission、Working group jointly formed by Tianjin Development and Reform Commission and other departments,The on-site office meeting was held in the project department of the first section of the Tianjin-Weifang high-speed railway constructed by the 14th Bureau of China Railway.。
At the office meeting,Tianjin Transportation Commission、Tianjin Development and Reform Commission and other units highly appraised the progress of the project construction of the 14th Bureau of China Railway.。The meeting pointed out,Tianjin-Weifang high-speed railway Project of China Railway Shisiju Group Co., Ltd.,The preliminary work is tense and efficient.、Scientific and powerful construction organization guarantee、Smooth and orderly resumption of work and production,To achieve the first quarter“A good start”Lay a solid foundation。
The First Section of Tianjin-Weifang high-speed railway undertaken by China Railway No.14 Engineering Group Co., Ltd,Located in Tianjin Binhai New Area,It mainly includes the Jingu Haihe Tunnel.、One subgrade section,The total length is nearly 7.Five kilometers。This construction section is the key project of the whole line of Tianjin-Weifang high-speed railway.,The scale of the project is large、A large number,Difficult in project organization and management。
Since the approach,The project team insists on planning first.,Complete the Pre-project planning at the fastest speed;Adhere to“Build a win-win situation”The guidelines for,Promote the early requisition and demolition work with high efficiency;Highlight the key and difficult points,Strengthen the management and control of key work nodes;Implement“Three modernizations and one new”,High-standard construction of high-quality projects in the era。
First quarter of 2023,Excellent achievements in many aspects on the whole line,Realized“Take the lead at the start of the race、Start sprinting”A good situation。
01 The first laboratory of the whole line to pass the acceptance
January 10,The central laboratory of the project department has successfully passed the evaluation and acceptance of the owner and the supervision unit.,It marks that the laboratory has become the first central laboratory that has successfully passed the acceptance test among all the participating construction units in Jinwei high-speed railway.,The conditions for carrying out the test and inspection work have been met.。The area of the laboratory is about 1650 square meters.,It is divided into office areas、Three functional areas of test operation area and living area。
02 The first new project site that has passed the acceptance and settled in the whole line
January 10,The construction of the project site has been completed and passed the acceptance.。11,The residence of the project department is settled.,It has become the first new project site in Jinwei high-speed railway to pass acceptance and be settled in.。
03 Undertake the first party building cloud class on the whole line
January 16,The Party Branch of Tianjin Command of Xiongan high-speed railway Company organized a cloud classroom activity for Party building in Tianjin and Weifang high-speed railway.,As the main venue, the conference room of the project department undertakes the first party building cloud class of the whole line.。
04 The first steel bar processing plant completed on the whole line
January 17,Completion of construction of steel bar processing plant of the project,It has become the first steel bar processing plant completed on the Tianjin-Weifang high-speed railway line.。
05 The first bid section of the whole line to complete the test pile
January 18,The first pile test of the project was successfully completed,It has become the first unit to complete the test pile on the whole line of Jinwei high-speed railway.。
06 The first mixing station of the whole line to pass the acceptance
January 18,The construction of the mixing station of the project has been completed and passed the acceptance,Become the first mixing station that has passed the acceptance of the whole line。
After the completion of Tianjin-Weifang high-speed railway,,It can complement Beijing, Tianjin and Hebei、Short board of high-speed railway development in coastal areas such as Shandong Peninsula,In the regional road network, a new high-capacity fast track will be formed in the eastern part of the Beijing-Shanghai high-speed railway.,Greatly enhance the Yellow River Delta and Beijing-Tianjin-Hebei、The interconnection level of the Yangtze River Delta and other urban agglomerations。
(China Railway 14th Bureau)
XCMG: Six bridges and two engines, XCA400L8 _ 1 is high-tech!
Set a New National Record, Sinotruk Heavy Truck Export Exceeds 14000 Vehicles in February!
Renovation of Patterns? Zhonglian Mining Machine "Customer Activity Day" Officially Opened
Good news of delivery | Batch delivery of 30 SJM 3090F wide-body dump trucks
XCMG Official 5m 1000W*2 Hand Push Operated Lifting Telescopic Mobile Metal Halide Lamp Balloon Light Tower
XCMG Official 5m Hand Push Lifting Telescopic Mobile Halogen Lamp Light Tower for Construction Site and Mining
XCMG Factory 9m Hydraulic Mast Diesel Generator Trailer Mobile LED Stadium Light Tower
XCMG Official 7m China New Mobile Diesel Generator Explosion Proof LED Work Light Tower for Sale