Midsummer,The expressway projects of Yunnan Trading and Investment Group are very busy.,Each project builder grasps the second quarter“Push forward the critical period of work、Golden season of project construction”,Sound the Horn of Fortification,Start Yunnan Trading and Investment Construction“Acceleration”。
Full sprint project completed and opened to traffic
June 13,Longest Tunnel of Mengla-Luchun Expressway in Yunnan Completed 183 Days Ahead of Schedule,It has laid a solid foundation for achieving the goal of opening to traffic.。Dali-Nanjian Expressway Project、The Lincang-Qingshuihe Port Expressway Project is being completed by the end of the year.,Only Baita Village Tunnel Remains、Shenchang Village Tunnel、Wangjiazhai tunnel。The subgrade works of Lincang-Shuangjiang Expressway Project have been completed accumulatively 100%、Bridge Engineering 99.7%、Tunnelling 99.3%、Pavement works 95.4%,Boshan Interchange to the end of the project is scheduled to open at the end of October.,The main remaining Tianshengqiao Tunnel of the whole line。
The section from Yangtouyan to Zhanglong of Yunxian-Lincang Expressway is planned to be completed and opened to traffic within this year.Nine kilometers have been completed and opened to traffic.,Only the remaining Daliangshan Tunnel。Ruili-Menglian Expressway“Not idle day and night、Every minute counts”The spirit of struggle,Targeted and clear objectives,Section from Mengsa Interchange to Mengsheng Interchange、The test section of pavement engineering from Ximeng Interchange to Menglian Langle Interchange has been started in May.,Roadbed、Bridge、The tunnel is advancing at full speed.,A total of more than 80 kilometers are planned to open to traffic in sections by the end of the year.。
Fully guarantee the construction elements of the project
Accompanied by the roar of the bridge-erecting engine,One piece is 30 meters long.、High 1.8 meters、Prefabricated weighing about 80 tonsTThe beam landed firmly on the abutment.,The first piece of Yongping-Changning ExpresswayTThe erection of the beam was successfully completed,Entrance Construction of Sujiazhuang Tunnel of Laoying-Banqiao Section Rerouting Project of Dali-Baoshan Expressway……A string of good news followed.,It demonstrates the firm belief that the mission of road builders must be achieved.。
Yao'an-Nanhua Expressway、Mengyuan-Guanlei Port Expressway、Yongping-Changning Expressway(Dali section)、Huize-Qiaojia Expressway、Menglian-Menghai Expressway、Mouding to yuanmou Expressway、Rerouting Project of Laoying-Banqiao Section of Dabao Expressway、National Highway NetworkG8512 Jinghong-Daluo Expressway(Menghai to Daluo Section)、Gongshan-Xiaopu Expressway and other projects are sprinting for construction.,Construction of Tunnel Face Entry of More than 10 Tunnel Control Projects。
At present,The Mojiang Bixi-Shuanglong Expressway has been fully started.,Some projects have achieved control projects.、Construction of temporary works started,33 mainline bridges of Yao'an-Nanhua Expressway、Six tunnels have been fully constructed.,Yao'an Interchange completed and opened to traffic,At the same time, Yao'an toll station was opened.。
Fully guarantee the investment and construction of the project
Prepare the investment plan for 2023 according to the actual situation of the project、Funding plan、Preliminary work plan、Construction General Contract Signing Plan、Promotion plan for implementation of entity project,Yunnan Trading and Investment Group Strengthens Supervision and Supervision of Traffic Opening Projects,Keep a close eye on key control projects,Construction general contractors with slow project progress,Take interviews to urge them to prepare enough machinery and equipment.、Construction personnel shall reasonably organize the construction。
To ensure the construction progress of the project under construction,Yunnan Trading and Investment Group has also carried out in-depth docking and implementation of the preliminary work of various projects.,Leaders take the lead in going to the forefront to solve the problems and difficulties in the early stage of the project,Organize each project company under construction to draw up the preliminary work promotion plan according to the actual situation of the project.,Realize wall chart operations、Press stubble and push forward。And set up a special work class.,Irregularly inspect the work difficulties of each project,Focus on control projects,Solve the problem on the spot,Formulate a plan、Negotiate to solve the problem of tunnel mud burst、Water gushing and other geological disasters,Coordinate and solve problems such as poor construction organization。Key work scheduling mechanism,Carry out comprehensive supervision in a timely manner、Check,Supervise the project to rectify the existing problems、Pin number,Fully promote project construction。
Next step,Yunnan Trading and Investment Group will make every effort to promote the Ruili-Nongdao Port Expressway、Xuanwei-Huize Expressway、Provincial RoadS11 Shizong to Qiubei(Qujing section、Wenshan section)Lijiang Yulong-Weixi Expressway、Xichou-Funing Expressway、Investment and construction of Maguan-Xichou Expressway Project,Strive to achieve full construction as soon as possible。Yunnan Net
XCMG: Six bridges and two engines, XCA400L8 _ 1 is high-tech!
Set a New National Record, Sinotruk Heavy Truck Export Exceeds 14000 Vehicles in February!
Renovation of Patterns? Zhonglian Mining Machine "Customer Activity Day" Officially Opened
Good news of delivery | Batch delivery of 30 SJM 3090F wide-body dump trucks
XCMG Official 5m 1000W*2 Hand Push Operated Lifting Telescopic Mobile Metal Halide Lamp Balloon Light Tower
XCMG Official 5m Hand Push Lifting Telescopic Mobile Halogen Lamp Light Tower for Construction Site and Mining
XCMG Factory 9m Hydraulic Mast Diesel Generator Trailer Mobile LED Stadium Light Tower
XCMG Official 7m China New Mobile Diesel Generator Explosion Proof LED Work Light Tower for Sale