● Lin TaigeCSM4000 Kazakhstan completed one month ahead of scheduleTKUAsphalt closure of upper base course of the sixth bid section project。
● Lin TaigeCSM4000 already for KazakhstanTKUThe second bid section project produces about 700,000 tons of asphalt mixture.
KazakhstanTKU&UDThe road improvement project is carried out by Tardikorgan-Kalbatau-Ust-Kamenogorsk and Usharal-Dostok port,The total length of the highway is 943.Four kilometers,The design speed is 120Km/h。
Lin Taige Helps CITIC KazakhstanTKU&UDHighway reconstruction project,Including KazakhstanKBIncluding highway projects,A total of 5 units were providedCSM4000 asphalt mixing plant,Now two of them are used by Shandong Road and Bridge Group.。
One of the two mixing stations is now in charge.TKUBid Section II of the Project,Entered in September 2018,So far,A total of nearly 700,000 tons of mixture were produced for the project.。The total length of this bid section is 88.3km,It is expected to open to traffic by the end of this year.。
Another oneCSM4000 is now in charge of Shandong Road and Bridge Group, which took over in May this year.TKUBid Section VI of the Project,This bid section is a new highway project.,The road is 70 kilometers long.,AdoptⅡClass I highway standard,Two lanes in both directions。With the help of Lintaige Asphalt Mixing Station,This bid section is on October 13.,Take the lead in completing the asphalt closure of the upper base course of the Abaizhou section,One month ahead of the expected construction schedule。
These two Lin Tai GeCSM4000 arrived in Kazakhstan by Central European train,The core components of the equipment, such as screening system、Metering system、Mixing system and precision components are placed inside the container,So as to reduce the impact of adverse weather conditions,Ensure the performance and service life of the whole machine。
Lin Taige is a century-old brand.,Its equipment is highly adaptable.、High stability is well-known in the international market.,And the standard full container design makes it more convenient.、Field construction、The safety performance is superior to that of the traditional frame type mixing station.。
At the same time,Lin Taige also provides on-site production guidance for users.、All-day online troubleshooting and other all-round technical support and after-sales service,Ensure smooth operation of production。
ResponsibleTKUGuo, the head of the second bid project, said.:“This kind of container packaging type mixing station,It is not only convenient and fast for transportation and installation,,Under adverse climatic conditions,Whether it's windy or snowy outside.,There is no impact on the equipment components housed in the container,This greatly enhances the stability and longevity of the device.。Only one door needs to be locked under the whole station.,No one can get in.,Anti-bad weather and safety aspects of field operations are in place.。”
Since May this yearTKUSince the commencement of the sixth bid,The project team is facing a serious shortage of asphalt reserves.、A variety of resources are scarce、Personnel recruitment is difficult and many other difficulties.,With the support of Lintaige Asphalt Mixing Station,Give full play to subjective initiative,UseCSMEfficient performance of 4000。As of October 13,Paving of upper base course completed 22.Three kilometers,Paving of lower layer 24.9 kilometers,At present, it has successfully completed the upper base asphalt maintenance plan formulated by the user.。
Next step,Keep your nose to the grindstone、Forge ahead,Two Lin Tai pavilionsCSM4000 will escort production,Two standards and six standards are advancing at the same time.,Strive to achieve the annual goal of double-layer asphalt paving on the whole line,To promote“The Belt and Road”Make greater contributions to high-quality development。
XCMG: Six bridges and two engines, XCA400L8 _ 1 is high-tech!
Set a New National Record, Sinotruk Heavy Truck Export Exceeds 14000 Vehicles in February!
Renovation of Patterns? Zhonglian Mining Machine "Customer Activity Day" Officially Opened
Good news of delivery | Batch delivery of 30 SJM 3090F wide-body dump trucks
XCMG Official 5m 1000W*2 Hand Push Operated Lifting Telescopic Mobile Metal Halide Lamp Balloon Light Tower
XCMG Official 5m Hand Push Lifting Telescopic Mobile Halogen Lamp Light Tower for Construction Site and Mining
XCMG Factory 9m Hydraulic Mast Diesel Generator Trailer Mobile LED Stadium Light Tower
XCMG Official 7m China New Mobile Diesel Generator Explosion Proof LED Work Light Tower for Sale