Half of the whole line runs through! The latest progress has been made in the construction of this expressway in Guangxi.

Half of the whole line runs through! The latest progress has been made in the construction of this expressway in Guangxi.

March 13, 2024

Recently,Phase I Project of Nanning Wuwei-Shangsi Section of Longsheng-Dongzhong Port Highway(Abbreviated as Wu-Shang Expressway Phase I Project)The right half of Fushan Bridge was successfully completed.,It marks that the first phase project of Wushang Expressway has ushered in a breakthrough in the whole line.,Break through the breakpoint of pavement construction,And provide convenience for that transportation of subsequent construction materials.,It has laid a solid foundation for the smooth completion and opening of the project.。

It is reported that,Wu-Shang Expressway Phase I Project,It starts near Naxi Village, Nanning City.,Route from north to south,Through Yan'an Town, Jiangnan District, Nanning City、Fangchenggang City, Shangsi County, Naqin Township,Finally, near Longlou Village, Naqin Township, Shangsi County,Connect to Shangsi-Fangchenggang Expressway。The total length of the route is 37.6km,The ratio of bridge to tunnel is 27.8%,Adopt the standard of two-way four-lane expressway,The design speed is 120km/h,Subgrade width is 27m。Set up 36 bridges,One tunnel,Naqi Junction Interchange、Yan'an Interchange、That Qin is interoperable、4 interchanges such as Longlou Hub Interchange,Yan'an Service Area 1,Yan'an、Naqin Interchange Toll Station 2。

After the Spring Festival this year,The project quickly resumed production.。So far,The project has completed a total investment of 3.4 billion yuan.,Accounting for 54% of total investment.62 of 600 million yuan%;Among,Subgrade works accumulatively completed 99%、Bridge and culvert works completed accumulatively 90%、Total completion of tunnel works: 95%、Housing construction projects completed a total of 90%、Pavement works 20%Cumulative completion。The whole line has formed a scene of rapid construction.,The subsequent construction of the bridge deck system and each structural layer of the pavement is in full swing。

Source:Guangxi News Network、Guangxi Daily

Featured

XCMG: Six bridges and two engines, XCA400L8 _ 1 is high-tech!

XCMG: Six bridges and two engines, XCA400L8 _ 1 is high-tech!

Set a New National Record, Sinotruk Heavy Truck Export Exceeds 14000 Vehicles in February!

Set a New National Record, Sinotruk Heavy Truck Export Exceeds 14000 Vehicles in February!

Renovation of Patterns? Zhonglian Mining Machine "Customer Activity Day" Officially Opened

Renovation of Patterns? Zhonglian Mining Machine "Customer Activity Day" Officially Opened

Good news of delivery | Batch delivery of 30 SJM 3090F wide-body dump trucks

Good news of delivery | Batch delivery of 30 SJM 3090F wide-body dump trucks

Trending Products

XCMG Official 5m 1000W*2 Hand Push Operated Lifting Telescopic Mobile Metal Halide Lamp Balloon Light Tower

XCMG Official 5m 1000W*2 Hand Push Operated Lifting Telescopic Mobile Metal Halide Lamp Balloon Light Tower

XCMG Official 5m Hand Push Lifting Telescopic Mobile Halogen Lamp Light Tower for Construction Site and Mining

XCMG Official 5m Hand Push Lifting Telescopic Mobile Halogen Lamp Light Tower for Construction Site and Mining

XCMG Factory 9m Hydraulic Mast Diesel Generator Trailer Mobile LED Stadium Light Tower

XCMG Factory 9m Hydraulic Mast Diesel Generator Trailer Mobile LED Stadium Light Tower

XCMG Official 7m China New Mobile Diesel Generator Explosion Proof LED Work Light Tower for Sale

XCMG Official 7m China New Mobile Diesel Generator Explosion Proof LED Work Light Tower for Sale

Engineering Machinery Vocabulary
TO TOP